13/07/2022

|

Completion of construction of a 150 / 20kV electrical substation

The PLC group creates in record time an HV / MV user substation serving a 15MW wind farm

PLC System S.r.l., a company directly controlled by PLC S.p.A., completed on 08/07/2022 the construction activities of the electrical and electromechanical works of a 150/20 kV HV / MT User Substation located in the Municipality of Molinara (BN), served by 5 Vestas V90 3.0 MW wind turbines, for a total of 15MW in the Municipality of Foiano di Valfortore (BN) and related to a contract with Leonardo Progetti S.r.l. (a company active in the development and management of plants from renewable sources).

This installation, which took place in record time and in only 150 days from the date of signing the contract with the customer, consolidates the positioning of PLC System as a reference operator in the electricity infrastructure segment that addresses its offer to Utilities, independent producers and financial investors.

CONDIVIDI

ARTICOLI CORRELATI

  • 19/09/2022

    |

    Read more
  • 15/09/2022

    |

    Read more
  • 02/08/2022

    |

    Read more